Form Project Header

From All n One's bxp software Wixi

Jump to: navigation, search

1 Overview

There is a form question type called Project Header. This complex question type provides key fields in the delivery of project tasks linked with the Project module.


The display of this data is usually done through a Gantt chart interface but tasks can be managed the same as any other CDA record.


This question type is not searchable by design.


2 Appearance in Form

project header 001.png


mappings


project header 002.png


3 Fields

Where possible we have attempted to keep the mappings to Microsoft Project as close as possible. https://support.office.com/en-us/article/Available-fields-reference-615a4563-1cc3-40f4-b66f-1b17e793a460


Field Title Description
intCDA_X_Id ID The ID field contains the identifier number that Project automatically assigns to each task or resource as you add them to the project.
strCDA_X_field_0_X Project The Project field shows the name of the subprojects where tasks, resources, or assignments originate.
strCDA_X_field_1_X Unique Parent A quick engine version of predecessors which allows only a single parent connection. (Not in MS Project)
strCDA_X_field_2_X Predecessors The Predecessors field lists the task ID numbers for the predecessor tasks on which the task depends before it can be started or finished.
strCDA_X_field_3_X Successors The Successors field lists the task ID numbers for the successor tasks to a task.
strCDA_X_field_4_X Active With the Active field, you can inactivate tasks to remove them from the Project plan. Inactive tasks remain available for use in a later phase, a later project, or for reporting or historical purposes. Inactive tasks no longer affect other tasks or the overall Project schedule.
strCDA_X_field_5_X Name The Name field contains the name of a task or a resource.
strCDA_X_field_6_X Notes The Notes field contains comments you can enter about a task, resource, or assignment.
strCDA_X_field_7_X Status The Status field indicates the current status of a task: Complete, On Schedule, Late, or Future Task.
strCDA_X_field_8_X Health The Health field contains the current status or condition, such as Early or Completed, of the current task as selected in the Health lookup table, which is shipped with Microsoft Project Server and can be modified to reflect an organization’s specific status measures.
strCDA_X_field_9_X Milestone The Milestone field indicates whether a task is a milestone.
strCDA_X_field_10_X Placeholder Placeholder tasks are manually scheduled tasks that do not have enough information to be scheduled. When you enter a manually scheduled task without a valid start or finish date and without a valid duration, Microsoft Project designates the task as having a Placeholder task mode.
strCDA_X_field_11_X Critical The Critical field indicates whether a task or an assignment's task has any room in the schedule to slip, or if a task is on the critical path.
strCDA_X_field_12_X Marked The Marked task field indicates whether a task is marked for additional action or identification of some kind.
strCDA_X_field_13_X Summary The Summary field indicates whether a task is a summary task.
strCDA_X_field_14_X Estimated The Estimated field indicates whether the task's duration is flagged as an estimate.
strCDA_X_field_15_X Deadline The Deadline field shows the date you enter as a deadline for the task. A deadline is a target date that indicates when you want a task to be completed.
strCDA_X_field_16_X Created The Created field contains the date and time when a task was added to the project.
strCDA_X_field_17_X Start The Start field shows the date when an assigned resource is scheduled to begin working on a task.
strCDA_X_field_18_X Finish The Finish field shows the date when a task is scheduled to be completed.
strCDA_X_field_19_X Duration The Duration field shows the total span of active working time for a task.
strCDA_X_field_20_X Percent (% Complete) The % Complete field contains the current status of a task, expressed as the percentage of the task's duration that has been completed.
strCDA_X_field_21_X Percent (% Work Complete) The % Work Complete field contains the current status of a task, resource, or assignment, expressed as the percentage of work that has been completed.
strCDA_X_field_22_X Cost The Cost field shows the total scheduled or projected cost for a task, resource, or assignment, based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work.
strCDA_X_field_23_X Work The Work field shows the total time scheduled on a task for all assigned resources, the total time to which a resource is scheduled on all assigned tasks, or the total amount of time scheduled for a resource on a task.
strCDA_X_field_24_X CreatedBy The Id of the original creator linked to the Client table of bxp. Not in MS Project.
strCDA_X_field_25_X Contact The Contact field contains the name of an individual responsible for a task.
strCDA_X_field_26_X Type A mapping field type for MS Project data storage. Task / Resource / Assignment Not available in MS Project.


4 Layout

From this the question type layout was designed and built against:

800px;