Form Project Header
From All n One's bxp software Wixi
Contents
1 Overview
There is a form question type called Project Header. This complex question type provides key fields in the delivery of project tasks linked with the Project module.
The display of this data is usually done through a Gantt chart interface but tasks can be managed the same as any other CDA record.
This question type is not searchable by design.
2 Appearance in Form
mappings
3 Fields
Where possible we have attempted to keep the mappings to Microsoft Project as close as possible. https://support.office.com/en-us/article/Available-fields-reference-615a4563-1cc3-40f4-b66f-1b17e793a460
Field | Title | Description |
---|---|---|
intCDA_X_Id | ID | The ID field contains the identifier number that Project automatically assigns to each task or resource as you add them to the project. |
strCDA_X_field_0_X | Project | The Project field shows the name of the subprojects where tasks, resources, or assignments originate. |
strCDA_X_field_1_X | Unique Parent | A quick engine version of predecessors which allows only a single parent connection. (Not in MS Project) |
strCDA_X_field_2_X | Predecessors | The Predecessors field lists the task ID numbers for the predecessor tasks on which the task depends before it can be started or finished. |
strCDA_X_field_3_X | Successors | The Successors field lists the task ID numbers for the successor tasks to a task. |
strCDA_X_field_4_X | Active | With the Active field, you can inactivate tasks to remove them from the Project plan. Inactive tasks remain available for use in a later phase, a later project, or for reporting or historical purposes. Inactive tasks no longer affect other tasks or the overall Project schedule. |
strCDA_X_field_5_X | Name | The Name field contains the name of a task or a resource. |
strCDA_X_field_6_X | Notes | The Notes field contains comments you can enter about a task, resource, or assignment. |
strCDA_X_field_7_X | Status | The Status field indicates the current status of a task: Complete, On Schedule, Late, or Future Task. |
strCDA_X_field_8_X | Health | The Health field contains the current status or condition, such as Early or Completed, of the current task as selected in the Health lookup table, which is shipped with Microsoft Project Server and can be modified to reflect an organization’s specific status measures. |
strCDA_X_field_9_X | Milestone | The Milestone field indicates whether a task is a milestone. |
strCDA_X_field_10_X | Placeholder | Placeholder tasks are manually scheduled tasks that do not have enough information to be scheduled. When you enter a manually scheduled task without a valid start or finish date and without a valid duration, Microsoft Project designates the task as having a Placeholder task mode. |
strCDA_X_field_11_X | Critical | The Critical field indicates whether a task or an assignment's task has any room in the schedule to slip, or if a task is on the critical path. |
strCDA_X_field_12_X | Marked | The Marked task field indicates whether a task is marked for additional action or identification of some kind. |
strCDA_X_field_13_X | Summary | The Summary field indicates whether a task is a summary task. |
strCDA_X_field_14_X | Estimated | The Estimated field indicates whether the task's duration is flagged as an estimate. |
strCDA_X_field_15_X | Deadline | The Deadline field shows the date you enter as a deadline for the task. A deadline is a target date that indicates when you want a task to be completed. |
strCDA_X_field_16_X | Created | The Created field contains the date and time when a task was added to the project. |
strCDA_X_field_17_X | Start | The Start field shows the date when an assigned resource is scheduled to begin working on a task. |
strCDA_X_field_18_X | Finish | The Finish field shows the date when a task is scheduled to be completed. |
strCDA_X_field_19_X | Duration | The Duration field shows the total span of active working time for a task. |
strCDA_X_field_20_X | Percent (% Complete) | The % Complete field contains the current status of a task, expressed as the percentage of the task's duration that has been completed. |
strCDA_X_field_21_X | Percent (% Work Complete) | The % Work Complete field contains the current status of a task, resource, or assignment, expressed as the percentage of work that has been completed. |
strCDA_X_field_22_X | Cost | The Cost field shows the total scheduled or projected cost for a task, resource, or assignment, based on costs already incurred for work performed by resources assigned to the tasks, in addition to the costs planned for the remaining work. |
strCDA_X_field_23_X | Work | The Work field shows the total time scheduled on a task for all assigned resources, the total time to which a resource is scheduled on all assigned tasks, or the total amount of time scheduled for a resource on a task. |
strCDA_X_field_24_X | CreatedBy | The Id of the original creator linked to the Client table of bxp. Not in MS Project. |
strCDA_X_field_25_X | Contact | The Contact field contains the name of an individual responsible for a task. |
strCDA_X_field_26_X | Type | A mapping field type for MS Project data storage. Task / Resource / Assignment Not available in MS Project. |
4 Layout
From this the question type layout was designed and built against: